Local ADU regulations, permit fees, setback requirements, and typical timelines for Santa Monica. Last updated 2026-05-27.

At a Glance

Santa Monica ADU Requirements

Setbacks (Side / Rear)
4 ft / 4 ft
Max Height (Detached)
16 ft

Attached ADU: up to 25 ft

Max Size (Detached / JADU)
1,200 / 500 sq ft
Parking Required?
No

Santa Monica is entirely within ½ mile of Big Blue Bus and Metro transit lines.

Est. Permit Fees
$7k–$16k

Plan check and permit fees; school fees apply for units over 500 sq ft.

Total Project Timeline
~11 months

Design 4 weeks · Permit 6 weeks · Build 36 weeks

Plain-language summary

In Santa Monica, a detached ADU requires a minimum 4-foot side setback and 4-foot rear setback. The maximum height for a detached ADU is 16 feet, while an attached ADU may be up to 25 feet. The maximum size for a detached ADU is 1,200 sq ft; a Junior ADU (JADU) is limited to 500 sq ft. Replacement parking is not required for most projects. Typical permit fees range from $7,000 to $16,000. A typical project takes approximately ~11 months from design start to move-in, including 4 weeks of design, 6 weeks for permit review, and 36 weeks of construction.

⚠️ ADU rules change frequently. Always verify current requirements with the Santa Monica Building & Safety Department before submitting plans. Official source →

Santa Monica-Specific Rules

What to Watch Out For

  • Properties west of Lincoln Blvd and south of Olympic Blvd may be in the Coastal Zone — a Coastal Development Permit is required.
  • Rent control (SMMC Chapter 4.36) applies to existing structures; new ADUs are generally exempt if permitted after 1995.
  • LADU HQ is located in Santa Monica — local permit expertise is particularly strong here.
Typical Process

How Long Does It Take to Get an ADU Permit in Santa Monica?

Design
4 weeks

Site study, floor plans, elevations, structural drawings.

Permit Review
6 weeks

Plan check, corrections, and permit issuance by Santa Monica Building & Safety.

Construction
36 weeks

Foundation, framing, MEP rough-in, finishes, final inspection.

Book your site visit

A licensed engineer on your lot, free.

30 minutes. We walk the property, figure out what's feasible, and answer any questions you have.

Next available — LA County

We're booking out further than usual. Click Book my free visit to see all available times.