ADU Rules in Manhattan Beach.

Local ADU regulations, permit fees, setback requirements, and typical timelines for Manhattan Beach. Last updated 2026-05-27.

At a Glance

Manhattan Beach ADU Requirements

Setbacks (Side / Rear)
4 ft / 4 ft
Max Height (Detached)
16 ft

Attached ADU: up to 25 ft

Max Size (Detached / JADU)
1,200 / 500 sq ft
Parking Required?
Yes

Manhattan Beach has limited transit access; replacement parking is generally required for garage conversions.

Est. Permit Fees
$10k–$20k

Manhattan Beach assesses a separate school impact fee for new ADUs.

Total Project Timeline
~12 months

Design 5 weeks · Permit 7 weeks · Build 38 weeks

Plain-language summary

In Manhattan Beach, a detached ADU requires a minimum 4-foot side setback and 4-foot rear setback. The maximum height for a detached ADU is 16 feet, while an attached ADU may be up to 25 feet. The maximum size for a detached ADU is 1,200 sq ft; a Junior ADU (JADU) is limited to 500 sq ft. Replacement parking is required for most projects. Typical permit fees range from $10,000 to $20,000. A typical project takes approximately ~12 months from design start to move-in, including 5 weeks of design, 7 weeks for permit review, and 38 weeks of construction.

⚠️ ADU rules change frequently. Always verify current requirements with the Manhattan Beach Building & Safety Department before submitting plans. Official source →

Manhattan Beach-Specific Rules

What to Watch Out For

  • Coastal Zone applies to properties within the coastal development overlay area (generally west of Sepulveda Blvd). CDP required.
  • Manhattan Beach has smaller average lot sizes; confirm lot coverage limits before designing.
  • Alley-loaded lots (common in the sand section) have specific ADU placement guidelines.
Typical Process

How Long Does It Take to Get an ADU Permit in Manhattan Beach?

Design
5 weeks

Site study, floor plans, elevations, structural drawings.

Permit Review
7 weeks

Plan check, corrections, and permit issuance by Manhattan Beach Building & Safety.

Construction
38 weeks

Foundation, framing, MEP rough-in, finishes, final inspection.

Book your site visit

A licensed engineer on your lot, free.

30 minutes. We walk the property, figure out what's feasible, and answer any questions you have.

Next available — LA County

We're booking out further than usual. Click Book my free visit to see all available times.