ADU Rules in Malibu.

Local ADU regulations, permit fees, setback requirements, and typical timelines for Malibu. Last updated 2026-05-27.

At a Glance

Malibu ADU Requirements

Setbacks (Side / Rear)
4 ft / 4 ft
Max Height (Detached)
16 ft

Height may be further restricted in Coastal Zone by view corridor protections.

Max Size (Detached / JADU)
1,200 / 500 sq ft
Parking Required?
Yes

Malibu has no transit proximity exemptions; parking replacement generally required.

Est. Permit Fees
$15k–$35k

Coastal Development Permit adds significant review time and fees. Septic system upgrades may be required.

Total Project Timeline
~15 months

Design 6 weeks · Permit 16 weeks · Build 44 weeks

Plain-language summary

In Malibu, a detached ADU requires a minimum 4-foot side setback and 4-foot rear setback. The maximum height for a detached ADU is 16 feet, while an attached ADU may be up to 25 feet. The maximum size for a detached ADU is 1,200 sq ft; a Junior ADU (JADU) is limited to 500 sq ft. Replacement parking is required for most projects. Typical permit fees range from $15,000 to $35,000. A typical project takes approximately ~15 months from design start to move-in, including 6 weeks of design, 16 weeks for permit review, and 44 weeks of construction.

⚠️ ADU rules change frequently. Always verify current requirements with the Malibu Building & Safety Department before submitting plans. Official source →

Malibu-Specific Rules

What to Watch Out For

  • Virtually all of Malibu is in the California Coastal Zone — a Coastal Development Permit (CDP) from the California Coastal Commission is required before construction.
  • Septic systems serve most of Malibu; ADUs typically require a septic expansion or new system (costly).
  • VHFHSZ: the entire city is in a Very High Fire Hazard Severity Zone. Class A roofing, ember-resistant vents, and 100-ft defensible space are mandatory.
  • Biological resources, ESHA (Environmentally Sensitive Habitat Area), and bluff-top setbacks may further restrict buildable area.
Typical Process

How Long Does It Take to Get an ADU Permit in Malibu?

Design
6 weeks

Site study, floor plans, elevations, structural drawings.

Permit Review
16 weeks

Plan check, corrections, and permit issuance by Malibu Building & Safety.

Construction
44 weeks

Foundation, framing, MEP rough-in, finishes, final inspection.

Book your site visit

A licensed engineer on your lot, free.

30 minutes. We walk the property, figure out what's feasible, and answer any questions you have.

Next available — LA County

We're booking out further than usual. Click Book my free visit to see all available times.