ADU Rules in Hidden Hills.

Local ADU regulations, permit fees, setback requirements, and typical timelines for Hidden Hills. Last updated 2026-05-27.

At a Glance

Hidden Hills ADU Requirements

Setbacks (Side / Rear)
4 ft / 4 ft
Max Height (Detached)
16 ft

Attached ADU: up to 25 ft

Max Size (Detached / JADU)
1,200 / 500 sq ft
Parking Required?
Yes

No transit access; replacement parking required.

Est. Permit Fees
$10k–$20k
Total Project Timeline
~13 months

Design 6 weeks · Permit 8 weeks · Build 40 weeks

Plain-language summary

In Hidden Hills, a detached ADU requires a minimum 4-foot side setback and 4-foot rear setback. The maximum height for a detached ADU is 16 feet, while an attached ADU may be up to 25 feet. The maximum size for a detached ADU is 1,200 sq ft; a Junior ADU (JADU) is limited to 500 sq ft. Replacement parking is required for most projects. Typical permit fees range from $10,000 to $20,000. A typical project takes approximately ~13 months from design start to move-in, including 6 weeks of design, 8 weeks for permit review, and 40 weeks of construction.

⚠️ ADU rules change frequently. Always verify current requirements with the Hidden Hills Building & Safety Department before submitting plans. Official source →

Hidden Hills-Specific Rules

What to Watch Out For

  • Hidden Hills is an entirely gated, private city — all streets and common areas are owned by the Hidden Hills Community Association (HHCA).
  • HHCA approval is required before any permit submittal; design review and association fees apply.
  • Equestrian zoning throughout: ADU placement must avoid horse trail easements and maintain equestrian access.
  • VHFHSZ designation applies; fire-resistant construction required.
  • Las Virgenes Municipal Water District (LVMD) connection fees apply.
Typical Process

How Long Does It Take to Get an ADU Permit in Hidden Hills?

Design
6 weeks

Site study, floor plans, elevations, structural drawings.

Permit Review
8 weeks

Plan check, corrections, and permit issuance by Hidden Hills Building & Safety.

Construction
40 weeks

Foundation, framing, MEP rough-in, finishes, final inspection.

Book your site visit

A licensed engineer on your lot, free.

30 minutes. We walk the property, figure out what's feasible, and answer any questions you have.

Next available — LA County

We're booking out further than usual. Click Book my free visit to see all available times.