ADU Rules in Beverly Hills.

Local ADU regulations, permit fees, setback requirements, and typical timelines for Beverly Hills. Last updated 2026-05-27.

At a Glance

Beverly Hills ADU Requirements

Setbacks (Side / Rear)
4 ft / 4 ft

State minimums apply. Hillside lots may require additional rear setback.

Max Height (Detached)
16 ft

Attached ADU: up to 25 ft

Max Size (Detached / JADU)
1,200 / 500 sq ft
Parking Required?
Yes

Replacement parking may be required depending on zone; verify with Planning Division.

Est. Permit Fees
$12k–$25k

Beverly Hills has one of the higher fee structures in LA County. Fees include Development Tax and school fees.

Total Project Timeline
~13 months

Design 6 weeks · Permit 10 weeks · Build 40 weeks

Plain-language summary

In Beverly Hills, a detached ADU requires a minimum 4-foot side setback and 4-foot rear setback. The maximum height for a detached ADU is 16 feet, while an attached ADU may be up to 25 feet. The maximum size for a detached ADU is 1,200 sq ft; a Junior ADU (JADU) is limited to 500 sq ft. Replacement parking is required for most projects. Typical permit fees range from $12,000 to $25,000. A typical project takes approximately ~13 months from design start to move-in, including 6 weeks of design, 10 weeks for permit review, and 40 weeks of construction.

⚠️ ADU rules change frequently. Always verify current requirements with the Beverly Hills Building & Safety Department before submitting plans. Official source →

Beverly Hills-Specific Rules

What to Watch Out For

  • Design Review Commission approval required for all new ADUs visible from the street.
  • Hillside properties (hillside overlay zone) have additional grading, drainage, and fire access requirements.
  • Geotechnical report may be required for lots with slopes greater than 15%.
  • HOAs may impose stricter aesthetic requirements; review CC&Rs before starting design.
Typical Process

How Long Does It Take to Get an ADU Permit in Beverly Hills?

Design
6 weeks

Site study, floor plans, elevations, structural drawings.

Permit Review
10 weeks

Plan check, corrections, and permit issuance by Beverly Hills Building & Safety.

Construction
40 weeks

Foundation, framing, MEP rough-in, finishes, final inspection.

Book your site visit

A licensed engineer on your lot, free.

30 minutes. We walk the property, figure out what's feasible, and answer any questions you have.

Next available — LA County

We're booking out further than usual. Click Book my free visit to see all available times.